Question: need help with C. Here is a CPM network with activity times in weeks (B(5) C16) (A7) G(3) ID6) E(4) F(8) ak a. Determine the

need help with C.
Here is a CPM network with activity times in weeks (B(5) C16) (A7) G(3) ID6) E(4) F(8) ak a. Determine the critical path. A-B-C-D O A-E-F-D O A E-G-C-D b. How many weeks will the project take to complete? Number of weeks 20 c. Suppose F could be shortened by two weeks and by one week. By how many weeks would this reduce the project duration? Number of weeks reducedStep by Step Solution