Question: need help with part c Activity immediate Predecessors A 6 2 B C D E F 3 5 3 5 BC D E E G

need help with part c
Activity immediate Predecessors A 6 2 B C D E F 3 5 3 5 BC D E E G a. Choose the correct network diagram for this project OA Q Start Finish Start Finish Start Finish Start Finish G b. Determine the critical path and project duration The critical path is path A-C-D-E-G and the project duration is 24 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.)Step by Step Solution