Question: need typed answer Create a Gantt chart for two jobs and identify on the chart the following two jobs that are reviewed on day 4:

need typed answer Create a Gantt chart for twoneed typed answer

Create a Gantt chart for two jobs and identify on the chart the following two jobs that are reviewed on day 4: Job 111 - It started on day 2 and should take 4 days, but has fallen behind by one day: Job 112 - It started on day 3 and should take two days. It finished early on day 4. TT TT Paragraph Arial 3 (12pt) T %D9 EESEES T'T Mashups - BE HTHLESS Path:p Words:0 Click Save and Submit to save and submit. Click Save All Answers to save all answers, Save All A