Question: : NEGOTIATION SIMULATION Course Code: CMNeg Course Name: Contract Management and Negotiations In - Class Activity Negotiation Simulation SELLER S INFORMATION - TECHNUTRONICS Brad Tennant,

: NEGOTIATION SIMULATION
Course Code: CMNeg
Course Name: Contract Management and Negotiations
In-Class Activity Negotiation Simulation
SELLERS INFORMATION - TECHNUTRONICS
Brad Tennant, Sales Manager for Technutronics, was developing a strategy for a negotiation session to be held with Gerald Stecklen, a buyer at Porto Corporation. Mr. Stecklen requested the meeting to discuss the quotation submitted by Technutronics for New Prod, a newly designed component.
Brads company submitted the quotation for New Prod in response to a request for quotation of 200,000 units plus a possible follow-on order of up to 200,000 units (Exhibit 1S). Working with the Engineering and Manufacturing staffs, Brad developed an estimate of manufacturing and tooling costs (Exhibit 2S).
The process required to produce the component was unique and somewhat complex. Therefore, quality control requirements for the part were quite involved. Furthermore, if material or equipment problems occurred, an additional $0.60 to $0.70 per unit would be required to produce the part at a level that satisfied the buyers requirements. Additional tooling might also be required beyond the quoted tooling charge of $40,000. However, Brad wanted to keep tooling charges to a minimum.
The Porto business would be beneficial to Technutronics since they were operating at 75% capacity. Porto was also a long-time customer. The contract would amount to approximately $1,000,000 plus a possible addition of $1,000,000 if the additional 200,000 units were realized.
Estimated direct costs to produce the component were $2.71(raw material + direct engineering + direct labor) of the $4.68 total cost to produce. Brad wanted to establish a per unit selling price that would cover all direct costs and significantly contribute to fixed costs and profit. Furthermore, he needed to consider the quality cost contingencies.
After some discussion by the management committee and a review of estimated costs for the part, a quotation was agreed upon. The quality cost contingencies were included and the possible tooling cost increases ignored ($4.68+ $ 0.70). A profit percentage of 10% was added ($0.54). Brad and his controller decided to quote $5.90 per unit plus $40,000 for tooling. Brad felt this bid to be competitive with other firms.
The manufacturing manager informed Brad he would make additional effort to develop statistical process control methods to highlight quality problems. Brad realized that the use of statistical methods could help reduce direct costs over time if Technutronics was successful in identifying and eliminating the sources of variability within the process. In addition, there were learning curve considerations for New Prod. However, Brad did not include any estimation of learning effects in the bid. Typically, items such as New Prod have a 90% learning curve.
Brads task was to develop his negotiation strategy and plan. He knew the contract was important to Technutronics, but they could not sustain a loss. He also knew that Porto did not possess the manufacturing capabilities for the part. The company had no option but to subcontract the component. Brad also knew that other suppliers were anxious for this business.
Exhibit 1B
Expected New Prod Delivery Schedule
Month Quantity
December 20,000
January 20,000
February 25,000
March 15,000
April 15,000
May 15,000
June 10,000
July 10,000
August 15,000
September 20,000
October 20,000
November 15,000
Total 200,000
Payment terms: Net 25
Transportation Terms: Sellers Plant, Freight Collect
Using Location: Detroit, Michigan
Exhibit 2S
Sellers Estimated Cost
(For 200,000 Units)
Total Cost Unit Cost
Raw Material: $497,000 $2.488
(0.4405 lbs./unit x $5.648/lb.)
Direct Engineering Labor:
Electrical Engineer
$17.50/hr. x 80 hrs. $ 1,400
Micro Associate Engineer
$11.25/hr x 1200 hrs. $13,500
Micro Technician
$10.50/hr. X 600 hrs. $ 6,300 $21,200 $0.016
Engineering Overhead: $21,000 x 125% $26,500 $0.1325
Direct Manufacturing Labor:
Machine Shop
$10.65/hr. x 1080 hrs. $11,502
Mechanical Assembly
$6.00/hr. x 2940 hrs. $17,640
Assembly Supervisor
$11.55/hr. x 500 hours $5,775
Production Manager
$14.50/hr. x 500 hours $7,250 $42,167 $0.2108
Manufacturing Overhead: $42,167 x 250% $105,418 $0.5272
SUBTOTAL $692,885
General and Administrative Costs:
$692,885 x 35% $242,510 $1.2126
TOTAL $935,395 $4.678
THE NEGOTIATION:
1. Prepare to negotiate a contract with Porto. Identify the key issues and the range of your position on those issues. Remember that price is not the only variable subject to negotiation.
2. What is your BATNA? Why?
3. What concessions do you plan to make during the negotiation?
4. What concessions do you expect on the part of the buye

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!