Question: ner I 1 , 2 and 3 Question 1 0 of 5 1 Which of the following is true related to activities on the critical

ner I
1,2 and 3
Question 10 of 51
Which of the following is true related to activities on the critical path?
A. They always include the most expensive activity
B. Fewer resources should be dedicated to these activities
C. Delays in these activities will delay in the entire project
D. They always include the activity with the longest processing time