Question: Net requirements are obtained by substracting on - hand inventory and scheduled receipts from gross requirements. Because the on - hand inventory of 1 8
Net requirements are obtained by substracting onhand inventory and scheduled receipts from gross requirements. Because the onhand inventory of in period exceeds the gross requirement in period the net requirements for period are The remaining units are carried into period In period the scheduled receipt of is added to the starting inventory of to give units. The gross requirements for period are so the net requirements for period are and the additional units are carried over to period Hence, the resulting net requirements for period are
The net requirements are phased back three periods because of the leadtime to obtain the timephased net requirements and the production schedule because these valves are produced internally Note that the scheduled receipts correspond to the defective parts returned to the company and reworked.
Homework Exercise #
Obtain the planned order release schedule for the Slide Assemblies using a lotforlot production rule
Homework Exercise #
An end item has the product structure diagram given in the figure below. Suppose that the MPS for the end item is the following:
tableWeeksMPS
Find the planned order release, assuming a lotforlot basis, for components F I, H C
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock