Question: Network Diagrams : Suppose we have a complete activity predecessor table below and we wish to create a network diagram highlighting the activity sequence for
Network Diagrams: Suppose we have a complete activity predecessor table below and we wish to create a network diagram highlighting the activity sequence for this project. Note that all duration times are in days.
1.0 Node Diagram. Show the Node Diagram. Complete all 8 items in each node label.
A. Conduct competitive analysis 3 -
B. Review field sales reports 2 -
C. Conduct tech capabilities assessment 5 -
D. Develop focus group data 2 A, B, C
E. Conduct telephone surveys 3 D
F. Identify relevant specification improvements 3 E
G. Interface with marketing staff 1 F
H. Develop engineering specifications 5 G
I. Check and debug designs 4 H
J. Develop testing protocol 3 G
K. Identify critical performance levels 2 J
L. Assess and modify product components 6 I, K
M. Conduct capabilities assessment 12 L
N. Identify selection criteria 3 M
O. Develop RFQ 4 M
P. Develop production master schedule 5 N, O
Q. Liaison with sales staff 1 P
R. Prepare product launch 3 Q
2.0 Gantt Charts: Show a Gantt chart that identifies the critical path for the project shown above.