Question: Exercise 10.20 Suppose we have a complete activity predecessor table below and we wish to create a network diagram highlighting the activity sequence for this
Exercise 10.20 Suppose we have a complete activity predecessor table below and we wish to create a network diagram highlighting the activity sequence for this project. Using MS Project, enter activities A through E, their durations, and their predecessors. Note that all duration times are in days. Project: Remodeling an Appliance Activity Duration Predecessors A Conduct competitive analysis 3 B Review field sales reports 2 C Conduct tech capabilities assessment 5 D Develop focus group data 2 A, B, C E Conduct telephone surveys 3 D
F Identify relevant specification improvements 3 E G Interface with marketing staff 1 F H Develop engineering specifications 5 G I Check and debug designs 4 H J Develop testing protocol 3 G K Identify critical performance levels 2 J L Assess and modify product components 6 I, K M Conduct capabilities assessment 12 L N Identify selection criteria 3 M O Develop RFQ 4 M P Develop production master schedule 5 N, O Q Liaise with sales staff 1 P R Prepare product launch 3 Q
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts