Question: NETWORK: PERT 2 - Spring 2022 Consider the following table: ACTIVITY PREC. ACT. tml COAL B D E A A B TIME ESTIMATES (days) to
NETWORK: PERT 2 - Spring 2022 Consider the following table: ACTIVITY PREC. ACT. tml COAL B D E A A B TIME ESTIMATES (days) to tr 6 6 6 3 4 6 2 4 6 3 5 7 1 3 5 4 4 AAAA 4 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.] 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time and the standard deviation (6) for the project round off the standard deviation to the nearest hundredth: two decimal places. 4) What is the completion time at 95% confidence level? 5) What is the likelihood of this project being completed earlier than 19 days? 6) Between 16 and 18 days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
