Question: Network scheduling process for AOA 1. Draw diagram? 2. Forward path to determine activities early-start times? 3. Backward path to determine activities late-finish times? 4.
Network scheduling process for AOA
1. Draw diagram?
2. Forward path to determine activities early-start times?
3. Backward path to determine activities late-finish times?
4. Float calculations?
5. Identifying critical activities?
| Task | Precedence | Time |
| a | - | 3 Weeks |
| b | - | 5 Weeks |
| c | a | 14 Weeks |
| d | a | 5 Weeks |
| e | b | 4 Weeks |
| f | b | 7 Weeks |
| g | d, e | 8 Weeks |
| h | g, f | 5 Weeks |