Question: Network scheduling process for AOA 1. Draw diagram? 2. Forward path to determine activities early-start times? 3. Backward path to determine activities late-finish times? 4.

Network scheduling process for AOA

1. Draw diagram?

2. Forward path to determine activities early-start times?

3. Backward path to determine activities late-finish times?

4. Float calculations?

5. Identifying critical activities?

Task Precedence Time
a - 3 Weeks
b - 5 Weeks
c a 14 Weeks
d a 5 Weeks
e b 4 Weeks
f b 7 Weeks
g d, e 8 Weeks
h g, f 5 Weeks