Question: NEW Amber Ale use a simple four-step process to prepare its products for shipment. Because of recent increases in demand, the company is setting up

NEW Amber Ale use a simple four-step process to prepare its products for shipment. Because of recent increases in demand, the company is setting up an assembly line to do the work. Draw for yourself a precedence diagram, group the tasks into workstations multiple workstations if neccesary, and calculate the expected output.

TASK PRECEDENCE TIME (MINS)

A None 5

B A 5

C B 4

D C 7

1) What is the minimum "takt time" if you have one worker? (one worker must perform all tasks) - takt time shows the time between two end products leaving the production zone

2) What is the minimum takt time if you have two workers? (Balance for straight line is imposed)

3) What is the minimum takt time if you have two workers? (Balance for straight line is not imposed)

4)What is the minimum takt time if you have three workers? (every operation is assigned to one worker) (Balance for straight line is imposed)

5)What is the minimum takt time if you have three workers? (every operation is assigned to one worker) (Balance for straight line is not imposed)

6)What is the minimum takt time if you have four workers? (every operation is assigned to one worker)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!