Question: Amber Ale use a simple five-step process to prepare its products for shipment. Because of recent increases in demand, the company is setting up an
Amber Ale use a simple five-step process to prepare its products for shipment. Because of recent increases in demand, the company is setting up an assembly line to do the work. How should the line be constructed if Amber needs a new product off the line every 10 minutes? Draw a precedence diagram, group the tasks into workstations, determine the efficiency of the line, and calculate the expected output for an eight-hourday.
.png)
Task Precedence None Time (mins) 8. C.D
Step by Step Solution
3.42 Rating (171 Votes )
There are 3 Steps involved in it
Desired cycle time Cd 10 Actual cycle ... View full answer
Get step-by-step solutions from verified subject matter experts