Question: Nina Automation Sdn Bhd estimates the data entry and verifying times for four jobs in the table below. Based on the information, in what order

Nina Automation Sdn Bhd estimates the data entry and verifying times for four jobs in the table below. Based on the information, in what order should the jobs be done if the company has one operator for each job? Please show the detailed calculation. Job Data Entry (Hours) Verify (Hours) A 2.5 1.7 B 3.8 2.6 1.9 1.0 D 1.8 3.0