Question: Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, six percent; fatigue, five percent; delay, eight

Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, six percent; fatigue, five percent; delay, eight percent. Use the Work Measurement Excel template to determine the standard time for this operation.
Work Observation
Element 123456789 Performance Rating
A 0.120.160.090.070.130.120.170.160.17115%
B 0.250.190.220.200.240.240.280.280.28100%
C 0.490.530.490.460.480.480.530.490.50110%
D 0.640.680.650.590.710.700.700.680.7095%
E 0.720.750.750.680.800.810.790.780.8290%
F 1.001.020.991.011.081.111.021.061.11110%
Round your answer to two decimal places.
minutesNine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, six percent; fatigue, five
percent; delay, eight percent. Use the Work Measurement Excel template to determine the standard time for this operation.
Work
Round your answer to two decimal places.
minutes
 Nine observations from a work measurement study using continuous timing are

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!