Question: NML Company is planning a large - scale change project. The change team is aware that some staff may resist the change and plans to
NML Company is planning a largescale change project. The change team is aware that some staff may resist the change and plans to introduce a bonus scheme which rewards achievement of the project's targets. Which of the stages of Kotter's eightstep change model for managing change will the bonus scheme help to fulfil?
Create the powerful coalition.Set the vision for change.Empower employees for broadbased action.Generate shortterm wins.