Question: NML Company is planning a large - scale change project. The change team is aware that some staff may resist the change and plans to

NML Company is planning a large-scale change project. The change team is aware that some staff may resist the change and plans to introduce a bonus scheme which rewards achievement of the project's targets. Which of the stages of Kotter's eight-step change model for managing change will the bonus scheme help to fulfil?
Create the powerful coalition.Set the vision for change.Empower employees for broad-based action.Generate short-term wins.