Question: Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Maximum weeks Reduced Crash Cost ($) Activity Crash Cost per Week ($) A N 500 1

Normal Time (weeks) Crash Time (weeks) Normal

Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Maximum weeks Reduced Crash Cost ($) Activity Crash Cost per Week ($) A N 500 1 900 1 400 B 4 4 600 3 700 1 100 ON 800 3 1,300 3 167 D Os 6 1,500 4 2,150 2 325 E OS 6 1,750 4 2.250 2 250 F 5 1,200 5 1,200 0 0 Os 6 1,500 4 1,800 2 150 G H H 2 500 2 500 0 0 AON network diagram: B H F Minimum project completion time = weeks