Question: Using the Information provided in the table, the network diagram and the project completion time - 25 weeks, reduce the completion time of the project

Using the Information provided in the table, the

Using the Information provided in the table, the network diagram and the project completion time - 25 weeks, reduce the completion time of the project by 3 weeks in the most economical way. Normal Time (weekel Orgah Time (weeke) Normal Cost ($) Maximum weeke Reduced Crash Cost ($) Activity Crash Coat per Week 9) 4 500 2. 900 400 600 3 700 1 00 10 5. 800 3 1.295 16 1165.00 D 6 1.500 2,150 2 229 6 1.750 2,250 2 250 5 1200 15 1.200 0 TO 1500 15 1.800 2 150 TO 500 3 500 10 (16) OS H3 DIG F/5) week 15