Question: Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows. table [ [ Activity

Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows.
\table[[Activity,Time],[A,3],[B,6],[C,2],[D,5],[E,4],[F,3],[G,9],[H,3]]
(1)
complete the project in 16 weeks. Thus, crashing of the project is necessary. The following information is relevant.
\table[[,Time (weeks),Cost ($)],[Activity,Normal,Crash,Normal,Crash],[A,3,1,900,1,700]]
\table[[,Time (weeks),Cost ($)],[Activity,Normal,Crash,Normal,Crash],[A,3,1,900,1,700],[B,6,3,2,000,4,100],[C,2,1,500,1,000],[D,5,3,1,800,2,400],[E,4,3,1,500,1,850],[F,3,1,3,000,3,900],[G,9,4,8,000,9,800],[H,3,2,1,000,2,000]]
(a) Formulate a linear programming model that can bre used to make the crashing decisions for this project. (The objective function should be the additional cost of crashin for activity i and yi= the amount of time activity i is crashed where i=A,B,C,D,E,F,G, and H.)
Min
s.t.
constraint A
constraint B
C depends on A
D depends on C
D depends on B
E depends on D
S depends on C
G depends on B
H depends on G
H depends on F
finish time for H
maximum crashing for A
maximum crashing for B
maximum crashing for C
maximum crashing for D
maximum crashing for E
maximum crashing for F
maximum crashing for G
maximum crashing for H
Solve the linear programming model and make the minimum cost crashing decisions. What is the amount of crash time (in weeks) for each activity?
\table[[Activity,Crash Time],[,]]
\table[[Activity,Crash Time],[A,],[B,],[C,],[D,],[E,],[F,],[G,],[H,]]
at is the added cost (in dollars) of meeting the 16-week completion time?
velop a complete activity schedule based on the crashed activity times.
\table[[Activity,\table[[Earliest],[Start]],\table[[Latest],[Start]],\table[[Earliest],[Finish]],\table[[Latest],[Finish]],Slack,\table[[Critical],[Activity]]],[A,,,,,,--Select-
 Norton Industries is installing a new computer system. The activities, the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!