Question: Note: Batch size of ) is single piece flow Refer to the process flow diagram for the aircraft production line above. Name the bottleneck step.
"Note: Batch size of is "single piece flow"
Refer to the process flow diagram for the aircraft production line above. Name the bottleneck step. Why do you think it is important to visualize your production system?
Identify the Cycle Time CT for each step Singlepiece flow What is the process CT
Identify the batch CT for each step Batch What is the process CT for a batch
We were able to determine customer demand aircraft per day assume one hour shift, and system is in steady state Which systemsBatch both will allow us to meet customer demand? Calculate the capacity and per unit CT for each system to justify your answer. Note: there is a difference between CT "per unit" and CT "per batch."
What is the throughput time TPT for an airplane when Batch size Batch Use actual cycle times above not takt time and assume FIFO ie no expediting
What is the lead time in minutes; order to delivery for aircraft when Batch size How much WIP is in this system assume pull system in steady state
What is the lead time in minutes; order to delivery for aircraft when Batch size How much WIP is in the system assume push system in steady state
Discuss the results above, and answer the following questions on your spreadsheet:
We're doing a great job! Customer demand is now aircraft per day. Do we need to make any improvements to the current singlepiece flow system to meet demand? YesNo why?
Before we make any improvements, what is the required takt time to meet customer demand of aircraft per shift assume single piece flow system and one hour shift
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock