Question: Question 25 16 polis Note the six distinct path times and variances for a project PERT chart individual activity times not shown Path Expected completion

Question 25 16 polis Note the six distinct path
Question 25 16 polis Note the six distinct path times and variances for a project PERT chart individual activity times not shown Path Expected completion time (days) Variance days) 35 28 What is the probability of completing the project within 30 days (Tel? Z-(Te Tey/Project Std Deviation, where Te client desired completion time: Terexpected project completion time, Project standard deviations, root of the Project Variance ritical path variance) 0.9838 0.8752