Question: Notes: (i) Total Slack / Float = Latest Finish Earliest Finish; or Latest Start Earliest Start. (ii) Tasks / activities with a total slack /

Notes: (i) Total Slack / Float = Latest Finish Earliest Finish; or Latest Start Earliest Start. (ii) Tasks / activities with a total slack / float of 0 (zero) need to be completed on-time to enable the project to be completed on-time. Therefore, they are critical tasks / activities, and probably Milestones, and together form the Critical Path (Aviation Project Management, Flouris & Lock 2008, pages 118 and 119).

QUESTIONS:

Using the precedence notation box outlined above and the table of information presented below:

1. Show the total duration of the project; and

2. Identify the critical tasks as Project Milestones and join them to show the Critical Path.

Using this table:

Task Time (days)

Immediate Predecessors or Independencies

A 24 -
B 18 -
C 30 A,B
D 8 -
E 30 C
F 14 D
G 31 E,F
H 36 G

Note: The (-) against tasks A, B and D

means that these tasks can all commence

at the same time after a start node.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!