Question: Notes: (i) Total Slack / Float = Latest Finish Earliest Finish; or Latest Start Earliest Start. (ii) Tasks / activities with a total slack /
Notes: (i) Total Slack / Float = Latest Finish Earliest Finish; or Latest Start Earliest Start. (ii) Tasks / activities with a total slack / float of 0 (zero) need to be completed on-time to enable the project to be completed on-time. Therefore, they are critical tasks / activities, and probably Milestones, and together form the Critical Path (Aviation Project Management, Flouris & Lock 2008, pages 118 and 119).
QUESTIONS:
1. Using the precedence notation box outlined above and the table of information presented below:
(i) Prepare a (free-hand) diagram of a project precedence network diagram;
(ii) Calculate the scheduling times and total slack/float for each activity;
| Task | Time (days) |
Immediate Predecessors or Independencies
|
| A | 24 | - |
| B | 18 | - |
| C | 30 | A,B |
| D | 8 | - |
| E | 30 | C |
| F | 14 | D |
| G | 31 | E,F |
| H | 36 | G |
| Note: The (-) against tasks A, B and D means that these tasks can all commence at the same time after a start node. |