Question: Numbers in parenthesis are the duration complete them. Use this information to find the following values for each of these activities: early start time, early

Numbers in parenthesis are the duration
complete them. Use this information to find the following values for each of these activities: early start time, early finish time, late start time, late finish time (Do in this Excel file). Based on this, find the slack time for each activity and identify the critical path. 2 Paint Window Sills (2) Install Windows (2) 2 Remove Siding (2) Add New Siding (6) Paint Exterior (2) 1 3 6 7 Remove Floor (1) Finish 4 5 Interior (3) Install New Floor (4)Step by Step Solution
There are 3 Steps involved in it