Question: Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon
Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities.
Time (weeks) | Cost ($1000s) | |||||
Activity | Description | Immediate Predecessor | Normal | Crash | Normal | Crash |
A | Plan needs | 10 | 8 | 30 | 70 | |
B | Order equipment | A | 8 | 6 | 120 | 150 |
C | Install equipment | B | 10 | 7 | 100 | 160 |
D | Set up training lab | A | 7 | 6 | 40 | 50 |
E | Conduct training course | D | 10 | 8 | 50 | 75 |
F | Test system | C, E | 3 | 3 | 60 |
Please answer the following questions.
- How can the project be displayed graphically to better visualize the flow of the activities?
- What are the critical activities, and what is the expected project completion time?
- Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost?
- What added project cost is required to meet the six-month completion time? (1 point)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts