Question: OM Tech is designing a product layout for its new product. This production line will run for 1 0 hours each day in order to
OM Tech is designing a product layout for its new product. This production line will run for hours each day in order to meet the forecasted demand of units per day. The following table describes the tasks necessary to produce this product:
Task
Time secs
Immediate Predecessor
A
none
B
A
C
B
D
B
E
C
F
DE
G
FWithout considering the forecasted demand, what is the minimum possible output rate unitsday from this production line?