Question: OM Tech is designing a product layout for its new product. This production line will run for 10 hours each day in order to
OM Tech is designing a product layout for its new product. This production line will run for 10 hours each day in order to meet the forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time (secs) Immediate Predecessor A 34 B 20 20 none A C 10 B D 16 B E 10 C F 24 D,E G 38 LL F