Question: Omega 2 Project Using the complexity weighting scheme and the function point complexity weighted table shown beiow, calculate the total function point count. Assume histonical

Omega 2 Project Using the "complexity weighting" scheme and the function point complexity weighted table shown beiow, calculate the total function point count. Assume histonical data suggest 6 function points equal one person-month and 5 people can work on the project. (Round onswers to the nearest whole numbers.) a. The total function point count is b. Calculate the estimated project duration: c. If 7 people are available for the project, what is the estimated project duration? d. If the project must be complete in six months, how many people will be needed for the project