Question: Omega 2 Project. Using the complexity weighting scheme and the function point complexity weighted table shown below, calculate the total function point count. Assume historical
Omega 2 Project. Using the "complexity weighting" scheme and the function point complexity weighted table shown below, calculate the total function point count. Assume historical data suggest five function points equal one person a month and six people have been assigned to work on the project. (Round the final answers to the nearest whole numbers.)
| Complexity Weight Table | ||||
| Number of inputs | 15 | Rated complexity | low | 2 points |
| Number of outputs | 20 | Rated complexity | average | 6 points |
| Number of inquiries | 10 | Rated complexity | average | 4 points |
| Number of files | 30 | Rated complexity | high | 8 points |
| Number of interfaces | 50 | Rated complexity | high | 15 points |
a. The total function point count is: b. Calculate the estimated project duration: c. If 20 people are available for the project, what is the estimated project duration? d. If the project must be completed in six months, how many people will be needed for the project?