Question: Omega 2 Project. Using the complexity weighting scheme and the function point complexity weighted table shown below, calculate the total function point count. Assume historical
Omega Project. Using the "complexity weighting" scheme and the function point complexity weighted table shown below, calculate
the total function point count. Assume historical data suggest function points equal one personmonth and people can work on
the project. Round answers to the nearest whole numbers.
a The total function point count is:
Total function point count
b Calculate the estimated project duration:
Estimated project duration
c If people are available for the project, what is the estimated project duration?
Estimated project duration
d If the project must be complete in six months, how many people will be needed for the project?
People needed to complete the project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock