Question: On any network path, the total float or schedule flexibility is measured by the amount of time that a schedule activity can be delayed or
On any network path, the total float or schedule flexibility is measured by the amount of time that a schedule activity can be delayed or extended from its early start date without delaying the late start date or violating a schedule constraint.
Question options:
True
False