Question: On this ACTIVITY, you will calculate PLANNED VALUE, ACTUAL COST, COST VARIANCE, and EARNED VALUE, using the same project discussed in the lecture for this
On this ACTIVITY, you will calculatePLANNED VALUE,ACTUAL COST,COST VARIANCE, andEARNED VALUE, using the same project discussed in the lecture for this module.
Below is theORIGINAL SCHEDULEfor the project:
CONSIDERING THE INFORMATION AND SCHEDULES PROVIDED ABOVE, ANSWER THE QUESTIONS BELOW. The BONUS QUESTION will not be graded, but MUST be answered
What is the TOTAL PLANNED COST for this project?
What is the TOTAL ACTUAL COST of this project?
What is the PLANNED VALUE on day
What is the EARNED VALUE on day
for this exercise, assume that task B was evenly split in days, according to the FINAL SCHEDULE provided
What is the project's COST VARIANCE on day
If you were tracking only COSTS as a KPI, and not EV what would be your conclusion about the performance of this project, if you compared the PLANNED COST and ACTUAL COST on day Explain your conclusions using the concepts presented in this module.
BONUS QUESTION: As a project manager, you seem to have overestimated the duration of task B What kind of biases could have caused this overestimation? review BIASES inModule
HOW TO SOLVE THIS ACTIVITY: Use Excel template
If using excel, I strongly suggest you create your own tables to solidify the concepts developed in this module and have a clear understanding of the relationships between planned value, actual cost, and earned value. That being said, here is atemplate for solving this activityDownload template for solving this activityyou still need to solve it but it is a little help to get to the final results
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock