One of the firm's existing projects needs to be completed earlier than planned. Use the following data
Fantastic news! We've Found the answer you've been seeking!
Question:
One of the firm's existing projects needs to be completed earlier than planned. Use the following data and the critical path and PERT methods to answer the questions that follow. Use the "most likely time" estimate (m) as the time estimate for the CPM analysis.
Activity | Immediate Predecessors | Times in Days | ||
a | m | b | ||
A | None | 1 | 3 | 5 |
B | None | 1 | 2 | 3 |
C | A | 1 | 2 | 3 |
D | A | 2 | 3 | 4 |
E | B | 3 | 4 | 11 |
F | C, D | 3 | 4 | 5 |
G | D, E | 1 | 4 | 7 |
H | F, G | 2 | 4 | 6 |