Question: Only answer if you're absolutely certain and show your work, please. The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB

Only answer if you're absolutely certain and show your work, please.

The following table represents a plan for a project:

PREDECESSOR JOB(S) TIMES (DAYS)
JOB NO. a m b
1 1 3 8
2 1 1 2 9
3 1 1 4 7
4 1 1 2 6
5 2 2 4 6
6 3 3 5 7
7 4 3 6 12
8 5,6 2 3 4
9 8 1 4 7
10 7 3 4 5
11 9,10 5 6 7

b. Indicate the critical path.

1-2-5-8
1-4-7-10-11
1-2-5-8-9-11
1-3-6-8-9-11

c. What is the expected completion time for the project? (Round your answer to 2 decimal places.)

Expected completion time days

d. You can accomplish any one of the following at an additional cost of $2,000 and if you will save $1,500 for each day that the earliest completion time is reduced, which action, if any, would you choose?

1. Reduce job 5 by two days.

Yes
No

2. Reduce job 3 by three days.

Yes
No

3. Reduce job 6 by two days.

No
Yes

e. What is the probability that the project will take more than 29 days to complete? (Round your answer to 2 decimal places.)

Probability

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!