Question: The following table represents a plan for a project: TIMES (DAYS) JOB NO. PREDECESSOR JOB(S) a m b 1 2 3 4 2 1 1
The following table represents a plan for a project:
| TIMES (DAYS) | ||||
| JOB NO. | PREDECESSOR JOB(S) | a | m | b |
| 1 | 2 | 3 | 4 | |
| 2 | 1 | 1 | 2 | 3 |
| 3 | 1 | 4 | 5 | 12 |
| 4 | 1 | 3 | 4 | 11 |
| 5 | 2 | 1 | 3 | 5 |
| 6 | 3 | 1 | 2 | 3 |
| 7 | 4 | 1 | 8 | 9 |
| 8 | 5, 6 | 2 | 4 | 6 |
| 9 | 8 | 2 | 4 | 12 |
| 10 | 7 | 3 | 4 | 5 |
| 11 | 9, 10 | 5 | 7 | 8 |
| What is the probability that the project will take more than 30 days to complete? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Other than the expected completion time you entered in part c above, do not round intermediate calculations. Round "z" value to 2 decimal places your final answer to 4 decimal places.) | ||||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts