Question: Only need CORRECT answer, thanks A project has three paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally,
Only need CORRECT answer, thanks
A project has three paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E-C has a length of 20 days. Which one of the following statements is true? Select one: a. A-D-C is the critical path. b. The expected duration of this project is 25 days. C. The expected duration of this project is 25 + 15 + 20 = 60 days d. A-B-C has the most slack. Check The county government has decided to redo the street you live on and plans to block the street off which causes you and your neighbour's considerable inconvenience. The project has three parallel paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 16 days, (ii) path A-D-E-H to install sidewalks with handicap capabilities that takes 22 days, and (iii) path A-F-G-H to repave the street including storm drains that takes 30 days. Which one of the following statements is true? Select one: a. The expected duration of the project is 30 + 22 + 16 = 68 days b. Path A-D-E-H has the most slack time. C. Path A-F-G-H is the critical path. d. Path A-B-C-H is the critical path. Check Which of the following is not considered a project? Select one: a. Production of soft drinks b. Introducing a new product c. Writing and implementing a computer program d. Building a bridge Check Which of the following is not a stage in the project life cycle? Select one: a. Organize b. Define c. Improve d. Close Check



Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock