Question: 1. A project has three paths. ABC has a length of 25 days. ADC has a length of 35 days. Finally, AEC has a length
1. A project has three paths. ABC has a length of 25 days. ADC has a length of 35 days. Finally, AEC has a length of 20 days.
Which one of the following statements is TRUE?
A. AEC is the critical path
B. ADC has the most slack
C. The expected duration of this project is 35 days
D. The expected duration of this project is 25 + 35 + 20 = 80 days