Question: Only select correct option Given the following information, draw a project network and answer the following question: Activity Predecessor Duration A None 4 B A

Only select correct option

Only select correct option Given the following information, draw a project network

Given the following information, draw a project network and answer the following question: Activity Predecessor Duration A None 4 B A C A D B 4 C, D 15 4s D G E, F The critical path is: O a. Cannot be computed O b. A-C-E-G O c. A-B-D-E-G O d. A-B-D- F-G