Question: onsider a two - step process. Step 1 consists of a single resource with a setup time of 3 0 minutes. Step 2 consists of
onsider a twostep process. Step consists of a single resource with a setup time of minutes. Step consists of a ingle resource without a setup. The processing time at both steps is minutes per unit. When we compute the ideal atch size, we find the formula does not produce a mathematically feasible answer. What is a valid explanation for this nusual finding?
Multiple Choice
Given equal processing times, the resource without a setup will always be the bottleneck; therefore, the batch size formula does not apply since matching of capacities is not possible.
Given equal processing times, the resource with a setup will always be the bottleneck; therefore, the batch size formula does not apply since matching of capacities is not possible.
The setup time should be reduced.
The resource without a setup has excess capacity.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock