Question: onsider the following: Activity Time Predecessor A 4 - - - B 2 - - - C 3 - - - D 1 A E

onsider the following:
Activity Time Predecessor
A 4---
B 2---
C 3---
D 1 A
E 4 B
F 8 C
G 2 D,E
Find the earliest project completion time?