Question: onstruct a PERT chart from the following task table ( make sure you also put TE and TL and slack time) 0 Time Estimate in

onstruct a PERT chart from the following task table ( make sure you also put TE and TL and slack time) onstruct a PERT chart from the following task

0 Time Estimate in (weeks) R P 1 1 2 3 2 3 3 5 5 2 4 4 1 1 2 1 2 4 4 4 6 8 3 2 Estimated Time (O+4R+6)/6 1.83 3.3 3.3 3.3 5 5 2.5 1.8 Preceeding Activity 1 1 2,3 4 4 6 5,7