Question: Operation Research 1 Question The following data for the activities of a project are available: ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 6 B -
Operation Research 1 Question
- The following data for the activities of a project are available:
| ACTIVITY | IMMEDIATE PREDECESSOR | DURATION (DAYS) |
| A | - | 6 |
| B | - | 4 |
| C | - | 7 |
| D | A,B,C | 5 |
| E | A,B,C | 6 |
| F | D | 9 |
| G | E | 4 |
| H | F,G | 8 |
| I | F,G | 6 |
| J | H | 7 |
Required:
- Draw the network, number the nodes, find the project completion time and calculate total, free and independent floats for the activities
- When the activity duration of G is doubled, identify the critical path .