Question: Operation Research 1 Question The following data for the activities of a project are available: ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 6 B -

Operation Research 1 Question

  1. The following data for the activities of a project are available:

ACTIVITY

IMMEDIATE PREDECESSOR

DURATION (DAYS)

A

-

6

B

-

4

C

-

7

D

A,B,C

5

E

A,B,C

6

F

D

9

G

E

4

H

F,G

8

I

F,G

6

J

H

7

Required:

  1. Draw the network, number the nodes, find the project completion time and calculate total, free and independent floats for the activities
  1. When the activity duration of G is doubled, identify the critical path .

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!