Question: Operations Management and TQM. Activity on Node and Arrow Solving problem: a. Construct an AON network based on the following: Activity Immediate Predecessors A B
Operations Management and TQM. Activity on Node and Arrow

Solving problem: a. Construct an AON network based on the following: Activity Immediate Predecessors A B C D A, B E b. Insert a dummy activity and event to correct the following AOA network: 3days 5 1 5 DAYS