Question: Optimistic Probable Pessimistic Expected Activity Preceding Activity Preceding A B A 7 9 1 4 C A 2 2 8 1 2 3 5 1

Optimistic Probable Pessimistic Expected
Activity Preceding
Activity Preceding
A
B
A
7
9
14
C
A
2
2
8
12
3
5
10
E
C
4
6
8
D
F
B
6
8,10
G
F
2
3
4
H
D, E
2
2
6
8
16
J
H
I, J
2
2
6
14
K
What is the probability of completion of the project AFTER week 40?
7634%
89%
45.5%
50%