Question: Optimistic Probable Pessimistic Expected Activity Preceding Time Time Time Time Variance . 7 9 14 B A 8 N N D 00 12 16 D

Optimistic Probable Pessimistic Expected Activity

Optimistic Probable Pessimistic Expected Activity Preceding Time Time Time Time Variance . 7 9 14 B A 8 N N D 00 12 16 D 3 5 10 E C 4 6 00 F B 6 8 10 LL 2. 3 4 H DE 2 00 N - G 6 8 16 H st 6 14 K 5 N N . Which activities form the critical path? A-B-E-F-K B-C-E-H-J-K A-C-E-H-J-K A-B-E-H-J-K

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!