Question: Optimistic Probable Pessimistic Expected Activity Preceding Time Time Time Time Variance A 7 9 14 B A 2 N 8 A 8 12 16 D

Optimistic Probable Pessimistic Expected Activity
Optimistic Probable Pessimistic Expected Activity Preceding Time Time Time Time Variance A 7 9 14 B A 2 N 8 A 8 12 16 D -- 3 5 10 E 4 6 8 B 6 8 10 G F 2 3 4 H DE 2 8 N - G 6 8 16 H 4 6 14 K 1J 2. 2 5 Which activities form the critical path? B-C-E-H-J-K A-B-E-H-J-K A-B-E-F-K A-C-E-H-J-K