Question: Optimistic Time Estimate(weeks) 2 Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessori Activity A 3 5 none B 2.4 4 5 A

Optimistic Time Estimate(weeks) 2 Most Likely

Optimistic Time Estimate(weeks) 2 Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessori Activity A 3 5 none B 2.4 4 5 A C 5 7 8 A 3 5 8 B, C B, C E 4 7 13 9 2. 5 D U O LUI - 4 5 6 E 6 6 9 Owuoi F 4. 7 10 G 2 3 3 (a) Choose the right network diagram. B D F H A E B F H A E G B F H A E G D F H A E G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!