Question: Options: A) 62 B) 51 C) 55 D) 53 E) 52 You are given the following data for a project: Activity Expected Time (days) Critical

Options:
A) 62
B) 51
C) 55
D) 53
E) 52
You are given the following data for a project: Activity Expected Time (days) Critical A 15 YES B 4. INO C 10 YES D 8 YES E 6 INO F. 12 YES G 7 YES I 10 NO What is the expected completion time of this projectStep by Step Solution