Question: Options - Activity D can be delayed by 1 day without delaying the overall project Float for Activity B is equal to 0, therefore, it
Options -
Activity D can be delayed by 1 day without delaying the overall project
Float for Activity B is equal to 0, therefore, it is an activity along the project's critical path
The latest Activity E can start without delaying the project is on day 12
Activity A is on the critical path which means LF=EF

Listen On a piece of paper, complete the network diagram below based on the activity Page 2: details within the chart provided. 2 Then, select ALL statements below that are correct for the network diagram that corresponds to the activities and dependencies outlined in the chart: Page 3: Activity Duration Predecessors Name (in days) 3 7 none B A C 6 Page 4: A D 12 B 4 E D.C ES Duration EF Page 5: Activity Name 5 LS Float LF Start Page 6: D End