Question: Order Due Processing # Date Time 139 day 39 18 days 145 day 57 30 days s 169 day 37 6 days s 146 day

Order Due Processing # Date Time 139 day 39 18
Order Due Processing # Date Time 139 day 39 18 days 145 day 57 30 days s 169 day 37 6 days s 146 day 58 10 days If today is day 1 and I am scheduling based on earliest due date, the flow time for order #146 is