Question: Order Due Processing # Date Time 139 day 12 days 39 32 days 10 days 146 day 58 30 days If today is day 20

Order Due Processing # Date Time 139 day 12 days

Order Due Processing # Date Time 139 day 12 days 39 32 days 10 days 146 day 58 30 days If today is day 20 and I am scheduling based on earliest due date, the flow time for order #146 is: O 84 32 O 64 054

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!